Tikhoretsky branch of PJSC "Kubanenergo" (a group of "Rossetti") in 2017 plans to invest more than 40 million rubles for the repair of equipment in five districts.

27.01.2017.jpg

These are objects that are included in the zone of responsibility Tikhoretsky electrical networks. The staff of the branch will conduct comprehensive repairs of equipment on the high-voltage substations "Novorozhdestvenskaya", "Pleasing" "Bolshevik" in the coach of the district, "Kugoeyskaya" in Krylovskaya area "Leninodarskaya" Pavlovsky district, "light", "Steppe" in Beloglinsky area and " Novopokrovcky ".

 

Energy collected otremontirovat15 high-voltage transmission core network. They need to replace obsolete supports, insulators, wire and ground wire. Experts will clear from the trees and shrubs around 30 hectares of protected zones transmission line.

 

Energy Tikhoretsk perform repair work on the distribution network. It is planned to replace around 400 towers, more than 3 thousand. 113 km insulators and conductors.

 

"Arrangements for repair of main and auxiliary equipment of substations and power lines are held annually with the approved frequency and strictly according to plan", - said the director of the coach of the branch of "Kubanenergo" Valery Gondar.

 

According to him, the main task of the branch - to improve the quality and reliability of electricity supply for both large enterprises and important social facilities as well as for residential customers in rural settlements.